黑料视频

PM: Lilia Gonzales and Christine Cook

CM: Ron Davenport

Architect: Jacobs, Carter and Burgess

Contractor: Austin Commercial

Substantial Completion Date: June, 2011

Budget: $42,000,000

This project involved the demolition of the old Osteopathic Hospital, which operated from 1946-2004. The scope of project was to construct a five (5) story Medical Education and Training facility. Only the first and second floors were included in the initial portion of the project, with the remaining upper three floors finished out at a later date. Shortly after the completion of the base building, the build-out of the upper floors began. These additional levels provided additional classrooms and lecture halls for the Medical Education and Training facility.

Project Status: Completed

Campus: 黑料视频 Health Science Center